[Reloaded]

Agent == Smith

Group Project Page

Recent News:

May 2, 2006 - Complete

Stand Up Meeting Notes

Reflection Workshop Notes

Process Critique

It has been a good class, and a busy semester. We had hoped that we would have more time, but believe that we have done well with what we have. Our demo tomorrow will be fun. The gui looks awesome, and the game is fun to play as well.

April 25, 2006 - Update

Stand Up Meeting Notes

Reflection Workshop Notes

Iteration II, is now complete. We have worked to smooth out the user experience in this iteration. The most notable change is that we have introduced a polished GUI. We also worked on the messages and events that are being passed so that the game is stronger, more fun, and less apt to break.

Our team members have finals that they would like to prepare for with the reamining days of this week. With that in mind, we have decided to shelf our game until after a final that we will be taking on Friday morning, and working to polish up phase III over the weekend, and at the beginning of next week. We are feeling very good about where the project stands now, and believe that we will have a finished, polished product to show on Wednesday, May 3.

April 20, 2006 - Update

    Standup Meeting
  • "Walking Skeleton" complete
  • Still struggling to get integrated builds running on Beast, Curtis to continue trying, and get help from teaching staff.
  • Jon to start working on making the GUI look good, and also to take a look at a serialization/deserialization issue
  • Andy writing unit tests
  • Chris to help Joe with creating tasks once Phase II is approved
  • Joe to write a proposed plan for phase II
  • Phase II to be approved by the team by Friday evening

April 18, 2006 - Update

Standup Meeting Notes

Things are progressing well. All of the tasks that we have slated for the 'walking skeleton' phase will be accomplished by Wednesday evening. This week we will work on finishing up the walking skeleton, and get continuous builds going with TFS and unit tests.

April 13, 2006 - Homework Assignment 9

3 Increments Plan

Good/Bad List

April 7, 2006 - Homework Assignment 8

The Construct

The above is a zip file containing our framework, a sample app, and a couple of other projects that were useful for testing.

Usage Document

The above file is a link to a page explaining how the framework can be used.

February 16, 2006 - Beginning

This will be our website for upcoming projects in CS3960-01. The stylesheet may change but the site location and contact information are good to go.